MISO-SPP IPSAC Recap — CSP progress, FERC waiver fallout, and a new solution window, 08/06/25

MISO-SPP IPSAC Recap — CSP progress, FERC waiver fallout, and a new solution window, 08/06/25

The August MISO-SPP IPSAC (hosted by SPP) meeting advanced the joint 2024–25 Coordinated System Plan (CSP), outlined a tentative TMEPs filing timeline, responded to FERC’s waiver denial by adding 15-year models, and opened a stakeholder solution idea window due Sept 5. Next IPSAC: Oct 24. Below is the full meeting overview.

Topics MISO-SPP IPSAC covered
  • TMEPs filing timeline (tentative): Committees on both sides of the seam continue reviewing cost allocation (MISO RECBWG/PAC; SPP CAWG/RSC/SAG), with an IPSAC touchpoint in October and a Q4 ’25 / Q1 ’26 target to file at FERC, assuming regional approvals.
  • CSP study updates: The RTOs reaffirmed a broader 2024–25 CSP scope to identify reliability, resilience, and transfer-enhancing projects, with potential FERC 205 changes to enable multiple-benefit recommendations.
  • FERC waiver denial, 15-year models: Because FERC rejected temporary exemptions in the JOA (multi-year analysis and regional project-avoidance metrics), MISO/SPP are building 15-year models for completion Oct/Nov; if results diverge materially from the 10-year runs, a second solution window may open. The RTOs are considering a 205 filing to support multi-benefit projects (e.g., Order 1920 benefits).
  • Modeling & analysis status: Blended/combined 10-year models are posted; analysis spans reliability, transfer, economic, plus an extreme-weather sensitivity (SPP’s ITP 2025 resilience model + MISO’s blended case). Preliminary transfer and reliability issues were summarized by area.
  • Solution idea window now open: Stakeholders are invited to submit transmission solution ideas and feedback on preliminary results via the form/email in the deck by Sept 5 (one idea per submission).
Dates & what’s next
  • Sept 5: Deadline for solution ideas & feedback (submission form/email in meeting materials).
  • Oct 24: Next IPSAC to review stakeholder input and draft solutions.
  • Through 2026: Draft solutions in Oct ’25 → recommendations in Dec ’25 → interregional cost allocation discussions Q4 ’25–2026 → approvals & JOA changes, then FERC filing in 2026.
Why it matters (for developers & load)
  • Longer view required: The shift to 15-year models could change needs and solutions; expect another solution window if results diverge.
  • Cost allocation still in play: TMEPs and CSP outcomes depend on parallel committee approvals; keep an eye on RECBWG/PAC and CAWG/RSC checkpoints leading into October.
  • Your input window is short: With solution ideas due Sept 5, sponsor concepts that relieve top transfer/reliability constraints highlighted in the preliminary results.
Let us help you shape a winning IPSAC submission
  • Constraint triage & screening: We’ll pinpoint the highest-value transfer and reliability constraints on the MISO–SPP seam.
  • Benefits framing: We’ll build a clear case across reliability, transfer, economic, and resilience metrics (aligned with current CSP/TMEP practices).
  • Submission materials: We will prepare an anonymized, submission-ready concept sheet and talking points for stakeholder discussions.

Have a seam project idea or want to pressure-test a concept before the solution window closes? Book a 20-minute MISO–SPP consult here, and we’ll turn your idea into a clear, submission-ready package.

View Meeting Materials here.