MISO PAC Meeting Critical Takeaways- 02/19/25 

MISO PAC Meeting Critical Takeaways- 02/19/25 

The latest MISO PAC stakeholder meeting covered a range of updates focused on improving interconnection processes, queue management, transmission planning, and cost estimation. Discussions highlighted recent regulatory approvals, new tools for tracking project milestones, and refinements to the ERAS proposal based on stakeholder feedback.

MISO PAC Meeting: Key Approvals and Updates
  • The PSC and IPWG Charter Management Plans were formally approved.
  • FERC accepted MISO’s Queue Cap Proposal on January 31, 2025, setting a cap at 50% of each planning region’s non-coincident summer peak load to better manage interconnection requests.
  • MISO plans to release a new GIA portal in summer 2025, designed to improve the application process, milestone tracking, and project visibility.
  • A Queue Caps Dashboard is in development to provide real-time queue capacity updates for each region.

Transmission Cost Estimation and Planning Updates: MISO will present the MTEP25 Transmission Cost Estimation Guide at the March 6 Planning Subcommittee meeting, incorporating cost updates and process improvements. Stakeholders are encouraged to submit feedback on MTEP Guiding Principles by March 24, 2025.

MISO-PJM Coordination & Affected System Studies: Redlines to Section 9.3.3 of the MISO-PJM JOA have been finalized, with feedback due by March 7, 2025. Until FERC approval, MISO will provide optional Affected System Study reports for impacted projects.

Interconnection Queue Enhancements: MISO is launching a one-time stakeholder feedback window to verify and update legacy generator interconnection service levels, aiming to resolve discrepancies and improve planning models.

ERAS Proposal and Developer Counterproposal
  • The ERAS proposal is advancing with final stakeholder input. Key refinements include stricter site control and COD requirements for eligible projects.
  • A developer counterproposal was presented, suggesting:
    • Prioritization of existing queue projects over ERAS applicants.
    • Stronger entry requirements and withdrawal penalties.
    • A ranking system to evaluate project eligibility based on resource adequacy needs.
  • The final ERAS package and Tariff redlines will be reviewed at the March 7 PAC meeting, with a FERC filing planned for mid-March.

Next Steps & Upcoming Deadlines
  • March 3 – Stakeholder feedback due on ERAS Tariff redlines.
  • March 6 – MTEP25 Transmission Cost Estimation Guide presented at Planning Subcommittee.
  • March 7 – Final ERAS package review at PAC.
  • Q3 2025 – Queue Cap Proposal application deadline.

The meeting underscored MISO’s ongoing efforts to streamline interconnection, improve planning transparency, and integrate stakeholder feedback into key initiatives. As these processes continue to evolve, stakeholder engagement remains critical in shaping the future of transmission planning and grid modernization.

Gain insights in the evolving power grid interconnection landscape. Dive into this month’s comprehensive stakeholder meeting summaries and blog insights to stay informed and ahead of the curve. For more information on ZEG and our services, schedule a free demo today!